A battery energy storage facility is being built in Litér, Western Hungary, with Siemens supplying the power distribution equipment.
One of Hungary’s largest energy storage facilities is being built at the Litér gas turbine power plant, owned by MVM Zrt. and operated by MVM Balance Zrt. The project will help strengthen the security of electricity supply in the region and support grid balancing as increasing amounts of renewable energy are fed into the power system.
The investment, worth more than EUR 10 million, involves the construction of a lithium-ion battery energy storage system with a power rating of 5 megawatts (MW) and a storage capacity of 10,000 kilowatt-hours (kWh). The facility will be connected to the public electricity grid through MAVIR’s Litér substation.

Illustration: Siemens NXAir air-insulated medium-voltage switchgear.
Developed by the MVM Group, the battery storage facility will have sufficient capacity to meet the daily electricity needs of more than 1,400 households.
The new energy storage facility will form part of a modern, highly efficient combined-cycle gas turbine system with a wide operating range, enabling it to contribute to the stability of the electricity grid in a sustainable manner.
For the project, Siemens Zrt. will supply four-panel, air-insulated medium-voltage switchgear to ensure reliable operation, working through its implementation partner, MVM XPert Zrt.